My PMP sample questions

Q 1 - At the end of 3 months in a 6 months long project EV is $14,000, PV is $15,000, AC is $17,500. Total budget for the project is $30,000. At the end of 3 months, project is:

A. Ahead of schedule and under budget
B. Behind schedule and over budget
C. Behind schedule and under budget
D. Ahead of schedule and over budget

Q 2 - A project has a total budget of $600,000. As of data date a project shows ACWP as $350,000, BCWP as $400,000 and BCWS as $425,000. Project is running -

A. Ahead of schedule with SPI = 1.06
B. Ahead of schedule with SPI = 1.14
C. Behind schedule with SPI = 0.94
D. Insufficient data to calculate SPI

Q 3 - In the above question, project is running -

A. Over budget with CPI = 0.94
B. Under Budget with CPI = 1.14
C. Under budget with CPI = 1.21
D. Insufficient data to calculate CPI

Q 4 - There are 3 projects to be chosen from. Project A has NPV of $680,000 with a payback period of 6 months, Project B has NPV of $600,000 with a payback period of 3 months and Project C has NPV of $725,000 with a payback period of 12 months. Based on this data, which project should be chosen -

A. Project A
B. Project B
C. Project C
D. Can not be determined with this data


Q 5 - There are 3 projects to be chosen from. Project A has NPV of $32,500, Project B has NPV of $40,000 and Project C has NPV of $45,000. Project C is chosen. The opportunity cost of project C is -

A. $32,500
B. $72,500
C. $45,000
D. $40,000

















Answers:

Q1 - B. SPI = EV / PV = 14000/15000 = 0.93 (which is less than 1), hence project is behind schedule. CPI = EV/AC = 14000/17500=0.8 (which is less than 1), hence project is over budget.

Q2 - C. SPI = EV/PV = BCWP/BCWS = 400000/425000=0.94 (which is less than 1), hence project is behind schedule with SPI = 0.94

Q3 - B. CPI = EV / AC = BCWP / ACWP = 400000/350000=1.14 (which is greater than 1), hence project is under budget with CPI = 1.14

Q4 - C. Project C will be chosen as this has the highest NPV.

Q5 - D. Opportunity cost is the cost of next best opportunity.


Here are the links for more practice questions -
  1. 3500 Question Exam Simulation CD-ROM
  2. 1000 PMP Exam Questions with Explanations, 5 Full Length Exams: Based on PMBOK 4th Edition
For more sample questions visit:
  1. PMBOK Guide 4th Edition Sample Questions
  2. More Sample Questions (PMBOK 4th Edition)

7 comments:

  1. Thanks a lot for this post! These group of question sure helps!

    It's great that I found this article. This will sure adds to my learning and help me prepare for the PMP exam. Great work!

    ReplyDelete
  2. Nathaniel, thanks for those great free questions. I found them usefull in my own studies. I also have some useful tool for free on my blog at www.thepreparedpm.com. thanks again. Midi

    ReplyDelete
  3. PMP Training Dubai is a very reputed Project Management Certification. The above shared questions are a good hint towards the importance of the certification. To prepare for PMP Certfication in Dubai start your PMP Training in Dubai with Delphi.

    ReplyDelete
  4. I am typically to running a blog and i really recognize your content. The article has really peaks my interest. I am going to bookmark your website and hold checking for new information. slots for real money

    ReplyDelete
  5. I have read your blog its very attractive and impressive. I like it your blog.

    kissanime alternatives

    ReplyDelete
  6. Join the Best PMP Training in Dubai pass your PMP Exam in First Attempt and gain PMP Certification in Dubai PMP Training Dubai

    ReplyDelete
  7. Thank for sharing this post. This provided sample questions really help. you can join best PMP Training Institute in Abu Dhabi and get PMP certification

    ReplyDelete