Q1 - Project manager acts as a coordinator or expediter in -
A. Weak matrix organization
B. Strong matrix organization
C. Projectized organization
D. Functional organization
Q2 - Due to change in the objectives of an organization the decision was taken to terminate a project. Which of the following project should be terminated -
A. Project where deliverables have been rejected by the client
B. Project where client is satisfied but it does not have a project charter
C. Project where two of the critical resources have left the organization
D. Project which has failed quality control checks
Q3 - You have joined the project mid-way as a project manager as the earlier project manager left the organization. To understand the project success criteria and the sign-off authority, you will look at -
A. Project Statement of Work
B. Project Scope Statement
C. Project Charter
D. Project Management Plan
Q4 - A new technology to develop a software has arrived in the market. As a project manager, you have a visibility into the client's roadmap and are aware that this technology will be used in your project. As a proactive measure, you have trained your resources in that technology. You have implemented -
A. Corrective Action
B. Defect Repair
C. Preventive Action
D. Organization training policy
Q5 - Your team is just about to implement the design when one of your team member approaches you with a new design for software development. This design will reduce the development time by half What is the FIRST thing you will do -
A. Implement the new design
B. Assess the impact of the new design on scope, cost & quality
C. Prepare a change request and take it to change control board
D. Refuse to make any change in the design now
Q6 - Requirements traceability matrix is an output of -
A. Collect Requirements
B. Define Scope
C. Create WBS
D. Control Scope
Q7 - Project scope statement, WBS & WBS disctionary constitute -
A. Schedule Baseline
B. Cost Baseline
C. Risk Baseline
D. Scope Baseline
Q8 - Which of the following BEST describes the purpose of Project Charter -
A. It identifies the stakeholders and their role on the project
B. It provides detailed scope of work
C. It authorizes the project manager to work on the project and apply resources
D. It lists all the risks associated with the project
Q9 - You are working in a construction company and are developing project scope statement for a new project. Which of the following is NOT part of Define Scope -
A. Project Charter
B. Product Analysis
C. Scope Verification
D. Alternatives Identification
Q10 - Which of the following is NOT an output of Close Project Phase -
A. Project Files
B. Final product
C. Project Closure documents
D. Project Statement of Work
Answers
Q1 - A - PMBOK Guide 4th edition P29, Sec 2.4.2
Q2 - B - A project does not have any existence without project charter, hence this should be closed
Q3 - C - PMBOK Guide 4th edition P78, Sec 4.1.3.1
Q4 - C - PMBOK Guide 4th edition P92, Sec 4.4.3.1
Q5 - B - Before taking any change request to Change control board, always assess the impact of the change on scope, cost, schedule and quality.
Q6 - A - PMBOK Guide 4th edition P111, Sec 5.1.3.3
Q7 - D - PMBOK Guide 4th edition P122, Sec 5.3.3.3
Q8 - C - PMBOK Guide 4th edition P73, Sec 4.1
Q9 - C - PMBOK Guide 4th edition P112, Sec 5.2
Q10 - D - PMBOK Guide 4th edition P101, Sec 4.6.3
Here are the links for more practice questions -
- 3500 Question Exam Simulation CD-ROM
- 1000 PMP Exam Questions with Explanations, 5 Full Length Exams: Based on PMBOK 4th Edition